Major pitch works at Edgar Street have taken a big step forward, with the new drainage system now completed and attention switching to rebuilding the playing surface.
The Edgar Street pitch after the mammoth overhaul
The project follows a season of disruption caused by waterlogging issues, which led to postponements and the relocation of three home games to Worcestershire.
The overhaul at Edgar Street Stadium is a full reset of the pitch structure, with earlier problems in the old drainage system uncovered during the works, including blocked and collapsed pipes that had contributed to the winter issues.
With drainage work complete, the old surface has been stripped and a new base laid. Seeding and fertilising have also been completed and the pitch returned to groundsman Ben Bowen.
Bowen, uncle of West Ham's Jarrod Bowen who is part-funding the work, has been sharing daily updates.
Here they are in full:
Day 1
The start of it all(finally)
Sprinklers all dug out/posts down/nets away
Day 2
Abit of sprinkler repairs (niggly things what has broke over last couple of weeks)
Materials arriving
Day 3
Not a huge amount going on today
Bits and bobs all tied up now
More sand coming in
Machinery being delivered
Day 4
We have action (geeeeeet up like)
1st lot of trenches going in
Laser levels done
Pipes arrived
All sand arrived
All stone arrived
πππππ
Day 5
Not been there today
By the looks pipes going down
5m centres are in
Day 6
Jon Morgan(kmm hire)Usk is our contractor doing the work at Hereford FC
Main carrier pipe is in
Trenches going in for new drainage
Pipe and stone going in
Full steam ahead
On target
ππππππππ
Day 7
More drainage going in
Half pitch done now
Had a chat with Jon earlier he says it’s all going well
Full steam ahead
Day 8
Not been there today been bizzy with some seeding pitches
By the looks on the camera drainage is nearly finished (I think,wouldn’t have a chuffin clue)anyway Jon is cracking on with it
πππππ
Day 9
Been to see Jon today nearly finished with drainage
All pipes in and connected
All stone in
Just started topping drain lines up with root zone (sand and part soil mix)shouldn’t be far off done tomorrow night with new drainage system
ππππ
Day 10
Not been there today so not much to report on it,
What Jon was saying yesterday he wanted drainage done today ready for stripping pitch off Monday
Will have a gander down there tomorrow
Day 11/12
Forgot to put something up last night
Anyway
Drainage all finished(interesting what they found with the old drainage)no wonder we had major problems
So today they started stripping off the pitch
2 passes taken off about 30mm(ish)depth
Couple more days should be all done
Then the headache will startπ€―π€―π€―
Day 13
pitch all stripped off
Powerharrow top surface
Verti drained
Started top dressing
A fair shift from Jon and geth
End of the tunnel is in sight
Day 14
Last of the sand went on
They have prepared seed bed ready for seeding and ferting tomorrow
This time tomorrow should be all done
Now that is a monster of a shift from Jon and geth fair play to them
Day 15
There we have it by tonight pitch will be complete
Levelled off
Seeded and fertilised
What a hell of a shift Jon and geth has done wow!!
Sprinklers getting changed over weekend(by me)
Couple of sprinklers and electrics being sorted next week(don’t worry they still all work just up grading)Matthew Gwynne (cmagri)
Final update
Well there she is our old girl is back in my hands
This has been a major major job on our pitch
New drainage installed
Complete revovations(don’t think it’s ever had this much done on it)
I feel de stressed now
Big thanks too Jon and geth from kkk hire you boys have put some sort of hours/ graft into this and made it right for us ππππ
Anyway that will do from me with the pitch updates for a while
See ya all at the back post soon
πJB20π